Many automation problems start before the equipment is ordered. If the requirement is vague, suppliers fill the gaps with their own assumptions, proposals become hard to compare, and the delivered machine may not handle the full product range or fit the line as expected.
A written requirement, often called a user requirement specification, avoids most of these problems. It does not need to be long, but it should be specific. This checklist covers what food and pet food manufacturers should define before requesting proposals.
1. Purpose and Scope
- What task will the equipment perform, and where in the line?
- What problem is it solving: labor cost, capacity, quality, safety, or several of these?
- What is in scope, and what is not, for example upstream conveyors or downstream equipment?
See our article on how automation reduces labor cost for help identifying the right task.
2. Products and Formats
List every product and format the equipment must handle, not just the highest-volume one:
| Detail | Examples |
|---|---|
| Product characteristics | Size, weight, shape, temperature, fragility, stickiness |
| Packaging | Bags, pouches, trays, cans, cartons, cases; materials and dimensions |
| Variation | Tolerances in size, weight and packaging between suppliers |
| Future products | Planned new formats or pack sizes |
Provide samples where possible. Equipment that handles the main product well but struggles with smaller variants is a common source of disappointment.
3. Rates and Operating Pattern
- required rate in units per minute, with normal and peak values
- shifts per day and days per week
- expected uptime and acceptable stoppages
- how the equipment should behave when upstream or downstream stops
4. Changeovers
- how many products and formats, and how often changeovers occur
- target changeover time and who performs it
- whether change parts, tool-free adjustment or recipe-based settings are required
Our SMED guide explains why changeover requirements matter.
5. Hygiene, Cleaning and Food Safety
- cleaning method: dry clean, wet clean or washdown, and chemicals used
- materials for product-contact surfaces
- hygienic design expectations, such as access for cleaning and avoiding product traps
- allergen management and changeover cleaning requirements
- the food safety standards and customer requirements your site follows
Involve your food safety and quality team in this section.
6. Space, Layout and Utilities
- available footprint and height, with a layout drawing
- access for operators, cleaning and maintenance
- electrical supply, compressed air, water and drainage
- environmental conditions such as temperature, humidity and dust
7. Integration and Controls
- connections to upstream and downstream equipment
- signals and data required, for example for production counts and downtime
- preferred control platform or brand, if your maintenance team has one
- operator interface language and access levels
8. Safety
- guarding and safety standards required at your site and in your country
- risk assessment responsibilities
- emergency stops, interlocks and safe access for cleaning and maintenance
9. Support, Training and Spare Parts
- installation and commissioning responsibilities
- operator and maintenance training required
- recommended spare parts and expected availability
- technical support response, remote support, and local service options
- warranty scope and what it covers
10. Acceptance Criteria
Agree in advance how the equipment will be tested:
- factory acceptance test: what will be demonstrated before shipping, with which products
- site acceptance test: rate, uptime, quality and changeover performance at your plant
- the duration of any performance run, and what counts as a pass
Clear acceptance criteria protect both the manufacturer and the supplier.
Using the Requirement
Send the same requirement to each supplier so proposals are comparable. Ask suppliers to state clearly where they meet, exceed, or cannot meet each point. Use the answers, together with a realistic ROI and payback estimate, to make the decision.
If you would like help defining a requirement or reviewing proposals, learn more about IvoryPear Technology and our automation planning support.
Frequently Asked Questions
What is a user requirement specification for automation equipment?
It is a written document describing what the equipment must do: the products and formats, rates, changeovers, hygiene, space, utilities, integration, safety, support and acceptance tests. It allows suppliers to propose suitable solutions and makes proposals comparable.
How detailed should the requirement be?
Detailed enough that two suppliers reading it would make the same assumptions about products, rates and conditions. Specific numbers and samples are more useful than general statements.
Should we specify the solution or the requirement?
Focus on what the equipment must achieve and the constraints it must work within. Specifying a particular technical solution too early can rule out better or more economical options.
Who should be involved in writing the requirement?
Production, maintenance, engineering, quality and food safety, and the operators who will use the equipment. Purchasing and finance should review the support, warranty and commercial sections.